Road Cost per Kilometre

Tonnage and budget per kilometre of road by carriageway width and layer thickness, for the United Kingdom.

Project dimensions

Full cost breakdown
Use this often? Press Ctrl+D (or ⌘+D on Mac) to bookmark this calculator so it's one tap away next time.

Quick answers

CarriagewayWidthArea per km40 mm50 mm100 mm150 mm
Single lane3.65 m3,650 m²343 t429 t858 t1,287 t
Two lanes7.3 m7,300 m²686 t858 t1,716 t2,573 t
Two lanes + shoulders11.0 m11,000 m²1,034 t1,292 t2,585 t3,878 t
Four lanes14.6 m14,600 m²1,372 t1,716 t3,431 t5,146 t
Four lanes + shoulders21.0 m21,000 m²1,974 t2,468 t4,935 t7,402 t

2026 prices

ItemLowTypicalHigh
AC surface course per tonne£72£88£115
HRA per tonne£82£100£128
SMA per tonne£95£118£150
Binder course per tonne£62£76£98
Base course per tonne£56£70£90
Recycled planings per tonne£8£18£32
Type 1 sub-base per tonne£12£18£28
Bitumen 40/60 per tonne£490£525£560
Driveway installed per m²£45£65£90
Car park installed per m²£35£50£72

Recommended thickness

ApplicationSurface courseBinder / base courseUnbound base
Footpath20–30 mm surface100 mm Type 1
Domestic driveway, cars20–25 mm surface50–60 mm binder100–150 mm Type 1
Driveway, vans or caravan25 mm surface60–70 mm binder150–200 mm Type 1
Private car park30 mm surface60 mm binder200 mm Type 1
Commercial car park40 mm surface60–80 mm binder225–300 mm Type 1
HGV yard40 mm surface100–150 mm binder and base300–450 mm Type 1
Estate road (adoptable)40 mm surface60 mm binder + 100 mm base225 mm Type 1
Trunk road40–50 mm surface60 mm binder + 150–250 mm baseCapping as designed
Asphalt road cross-sectionFive stacked pavement layers from the wearing course at the top through binder course, base course, unbound sub-base and the compacted subgrade, each labelled with its typical thickness.Asphalt road cross-sectionWearing course40–50 mmBinder course50–80 mmBase course80–150 mmSub-base (aggregate)100–300 mmSubgrade (soil)compactedAsphaltCalculatorPrice.com
Asphalt road cross-section — Wearing course, Binder course, Base course, Sub-base (aggregate), Subgrade (soil).

What moves the price

FactorEffect on priceWhy
Distance from the plantVery highHot mix must arrive above 130 °C, which limits a plant to roughly an hour's haul. Sites with two or three plants in range pay noticeably less than sites served by one.
Bitumen binder costHighBinder is 4.5–6% of the mix by weight but 25–35% of its cost, and it tracks crude oil with a lag of two to four months.
SeasonMedium-highPlants concentrate output into the paving season. Prices peak in mid-summer and soften at each end of the season.
Order sizeMediumBelow about 5 tonnes a small-load surcharge usually applies. Above a few hundred tonnes the rate becomes negotiable.
Mix specificationMediumPolymer-modified and stone mastic mixes cost 25–50% more per tonne than standard dense-graded material.
Aggregate supplyMediumRegions that import aggregate carry that cost straight into the mix price.
Access and site constraintsMediumNarrow access, weight-restricted bridges or overhead cables force smaller vehicles and raise the delivered rate.
Recycled contentLow-mediumHigher permitted recycled content lowers the plant's raw material cost.

Ordering and delivery

What the plant needs from you

Delivery vehicles

VehicleTypical payloadBest suited to
Rigid tipper (4-wheel)6–8 tVery tight access, small domestic work
Rigid tipper (6-wheel)10–14 tDomestic drives, restricted sites
Rigid tipper (8-wheel)16–20 tThe usual default for driveways and small car parks
Artic tipper26–29 tLarger car parks and road work with good access
Insulated / thermal bodyas aboveLonger hauls, cold weather, thin surfacing
Material transfer vehicle25 t+Continuous paving, eliminates segregation

A part-load at the end of a job is common. It is often worth increasing the design thickness slightly to fill the last vehicle rather than paying a small-load surcharge on two or three tonnes.

Waste and compaction allowance

Loose material behind the paver occupies roughly 20% more volume than the finished compacted surface. Add edge trimming, material left in the vehicle body and normal measurement tolerance, and you need an allowance on top of the calculated tonnage.

SituationAllowanceReason
Simple rectangle, machine-laid, experienced crew5%Minimal trimming and predictable compaction
Standard driveway or car park10%Normal edge detail and some hand work at the perimeter
Curved edges or several separate zones15%More offcuts and more hand placement
Hand-laid work and small patches15%Hand compaction is less consistent
Recycled planings15–20%Higher compaction factor and less predictable spread
Unbound granular base20–25%Significant consolidation under the roller

Round the final figure up to the nearest half tonne. Being short means a cold joint in the middle of the surface and a second delivery charge, which costs far more than the extra material would have.

Maintenance schedule

IntervalActionWhy it matters
Within the first 48 hoursKeep all vehicles offThe mat is still cooling and takes a permanent impression easily.
First 30 daysAvoid turning the wheel while stationary; support trailer jacks on a boardThe binder has not fully hardened and point loads leave marks.
Within 6–12 monthsFirst surface dressing or seal, if specifiedSlows oxidation of the binder. Applying it sooner traps volatiles and softens the surface.
AnnuallySweep, clear drainage, inspect edges and jointsStanding water at an edge is the most common cause of premature failure.
Every 1–2 yearsSeal any cracks that have appearedA sealed crack costs a fraction of the pothole it becomes.
Every 3–5 yearsReseal and, on car parks, re-lineRestores surface texture and appearance.
Every 10–15 yearsConsider a surface course overlayResets the wearing layer while the structure below survives.
20–25 yearsFull reconstructionOnly when the structure itself has failed, not merely the surface.

Deferred maintenance compounds quickly. A crack sealed early costs very little; the same crack left for two winters admits water, softens the base and becomes a full-depth patch. The economics of surfacing maintenance are almost entirely about intervening before water reaches the layers below.

The base underneath

The unbound layer under the surfacing does more structural work than the surfacing itself, and it is where most premature failures actually originate. A thinner bound layer over a deep, well-compacted, free-draining base will outlast a thicker bound layer over a shallow one.

SubgradeApproximate CBRBase under domestic accessBase under commercial
Well-graded gravel20–40100 mm150 mm
Sand, well drained10–20100–150 mm150–200 mm
Silty sand6–10150 mm200 mm
Loam5–8150–200 mm200–250 mm
Silty clay3–5200–250 mm250–300 mm
Heavy clay, poorly drained2–3250–300 mm plus geotextile300–450 mm plus stabilisation
Peat or organic soilunder 2Excavate and replaceExcavate and replace

Two additions repay their cost on marginal ground: a separation geotextile between the subgrade and the granular layer, which stops stone punching down into soft clay and can save 50–100 mm of aggregate; and proof-rolling with a loaded vehicle before any stone is placed, which finds the soft spots while they are still cheap to deal with.

Remember that the granular base is usually the larger tonnage of the two. A 100 m² area with 200 mm of base at 2,100 kg/m³ needs 42 tonnes of stone against roughly 12 tonnes of surfacing at 50 mm. Budget and order for both.

Calculator

Frequently asked questions

How many tonnes do I need?

Area in m² × compacted thickness in m × 2.35. A 100 m² area at 50 mm needs about 11.8 tonnes.

How many m² does a tonne cover?

About 8.5 m² at 50 mm compacted.

What allowance should I add?

10% for standard work, 5% for simple machine-laid rectangles, 15% for curved or hand-laid areas.

Does the calculator handle several areas?

Yes — add a zone per shape, each with its own thickness and mix type. Multi-layer structures and irregular sites are entered directly.

Which standards apply?

BS EN 13108 and BS 594987, administered by National Highways and the Specification for Highway Works.

Sources and further reading

2026 Q3

Last reviewed: Next review: November 2026 Reviewed by: AsphaltCalculatorPrice Editorial TeamRegion: United Kingdom