Tonne to m²

Type into any field and the others update instantly.

Project dimensions

Use this often? Press Ctrl+D (or ⌘+D on Mac) to bookmark this calculator so it's one tap away next time.

Type into any field and the others update instantly.

Density by mix type

DesignationDescriptionDensity (kg/m³)Typical useStandard
AC 10 surfAsphalt concrete surface course, 10 mm2,340Surface course 25–40 mmBS EN 13108-1
AC 14 surfAsphalt concrete surface course, 14 mm2,350Surface course 40–50 mmBS EN 13108-1
HRA 30/14Hot rolled asphalt with pre-coated chippings2,290Traditional surface courseBS EN 13108-4
SMA 10 surfStone mastic asphalt2,400High-traffic surface courseBS EN 13108-5
Thin surface course systemProprietary thin surfacing2,320Surface course 20–40 mmBS EN 13108-2
AC 20 binAsphalt concrete binder course, 20 mm2,360Binder course 50–80 mmBS EN 13108-1
AC 32 baseAsphalt concrete base, 32 mm2,370Base 80–150 mmBS EN 13108-1
EME2High-modulus base2,435Heavy-duty baseBS EN 13108-1 / CD 226
Porous asphaltPA 202,000Drainage surface courseBS EN 13108-7
Recycled planingsReclaimed asphalt planings2,000Drives, hardstanding, sub-baseBS EN 13108-8
Type 1 sub-baseGranular sub-base2,100Unbound sub-base 100–300 mmSHW Clause 803
Bitumen 40/60Paving grade binder1,030Tack coat and binder onlyBS EN 12591

Coverage per tonne

Compacted thicknessm² per tonnetonnes per 100 m²tonnes per 1,000 m²
20 mm21.34.7047.0
25 mm17.05.8858.8
30 mm14.27.0570.5
40 mm10.69.4094.0
50 mm8.511.75117.5
60 mm7.114.10141.0
70 mm6.116.45164.5
80 mm5.318.80188.0
100 mm4.323.50235.0
150 mm2.835.25352.5
200 mm2.147.00470.0

Calculator

Waste and compaction allowance

Loose material behind the paver occupies roughly 20% more volume than the finished compacted surface. Add edge trimming, material left in the vehicle body and normal measurement tolerance, and you need an allowance on top of the calculated tonnage.

SituationAllowanceReason
Simple rectangle, machine-laid, experienced crew5%Minimal trimming and predictable compaction
Standard driveway or car park10%Normal edge detail and some hand work at the perimeter
Curved edges or several separate zones15%More offcuts and more hand placement
Hand-laid work and small patches15%Hand compaction is less consistent
Recycled planings15–20%Higher compaction factor and less predictable spread
Unbound granular base20–25%Significant consolidation under the roller

Round the final figure up to the nearest half tonne. Being short means a cold joint in the middle of the surface and a second delivery charge, which costs far more than the extra material would have.

Standards and who administers them

Surfacing work in the United Kingdom is specified under BS EN 13108 and BS 594987, administered by National Highways and the Specification for Highway Works. In practice that governs three things you will see on any quotation or drawing:

For private domestic work none of this is legally binding, but the same physics applies. Asking a contractor which specification they are working to, and getting the compacted thickness written into the quotation in millimetres, is the single most useful thing you can do to make competing quotations comparable.